Roosevelt Modernization
-
A $92 million investment in North 欧美巨乳色情片.
Phased Construction began Spring 2015
Phase 1 Buildings ready for use: Fall 2016
Phase 2 Buildings ready for use: Fall 2017
Phase 3 Construction completed:
January 2018Roosevelt Modernization FAQ
FAQ's in EspañolArchitect
Contractor
Roosevelt High School is one of three high schools that are being modernized as part of the 2012 School Building Improvement Bond.
Read the RooseveltFall 2017 Project Update here Español | Soomaaliga
-
Project Updates/Information
Roosevelt Project Completed in January 2018Landscaping and site work was wrapped up in December of 2017 and when students & staff returned from winter break in January 2018 the full modernization of Roosevelt was complete.Phase 3 Modernization Site Work & LandscapingThe construction crews are working on finishing up Phase 3 of Roosevelt's modernization project. They are busy landscaping the front of the 1921 building with new trees, bushes, and grass and finishing up the large bio-swales and covered bike racks. The Autoshop building at the North end of the site has been completely demolished and hauled off site. The baseball/softball field is getting new dugouts, backstops, and other equipment. Some of this work will continue into the Spring, but will be ready for the first league game.Roosevelt students are taking advantage of new facilities (Fall 2017)Roosevelt students are that were made possible through the 2012 Bond. , and .Phase 2 Modernization complete-1921 building reopens (Aug 2017)Work on the 1921 building is now complete and active construction on Roosevelt's buildings has come to an end. The Historic 1921 building is fully modernized and ready for use. The main entrance and administration offices have returned to their former places. The expanded Commons area and Commons Courtyard are complete. Also added are 19 additional classrooms, 3 New Science labs, several new offices, a new Head Start Day Care, a security office, and a shared-use computer lab. The beloved clock tower has been given a full makeover and will once again be a functioning timepiece. The school is now fully modernized. Phase 3 site work and landscaping will continue for a few more months.Phase 2 of Roosevelt’s modernization, is nearing completion (July 2017), Phase 2 of Roosevelt’s modernization, is nearing completion. Along with a new roof and refurbished windows, the . On the inside, classrooms, labs and community spaces on all three levels are getting finish painting, flooring, and . Furniture is being moved into the science labs.
In the fall the student commons will expand inside of the building while outside, will open. Finishing on the courtyard is underway with bricks from the old cafeteria being in in the new courtyard.
Phase 3 Construction is also underway continues to January of 2018
The 3rd phase of the modernization of Roosevelt, which involves site work, landscaping and the demolition of the old cafeteria and library buildings is underway and will continue into the fall. When staff and students return in late August around some of the site and areas of exposed ground that are being prepared for landscaping. Completion of Phase 3 is set for January of 2018.Roosevelt goes solar
Roosevelt has two roof-top solar panel installations and some additional window awning installations for a total capacity of 134.79 kW. of generated electricity. Since their installation, the solar panels have provided the equivalent energy savings of 58 vehicles being taken off the road or 249 trees being planted and has prevented nearly 7,650 kg of carbon dioxide emissions (the main culprit in climate change) from entering the atmosphere.New classrooms and offices taking shape (April 2017)– phase 2 of Roosevelt’s modernization - is picking up steam. of the west wing is now complete with . On the first floor, west and south wings metal stud walls are now starting to be covered with drywall.In the east wing’s first floor, and Drywall has been added at the underside of ceiling to act as a fire barrier.
On the second floor of the west wing and mechanical, electrical, and The south wing of the second floor is being mechanically roughed-in and fire sprinkler installation is underway. On the east wing, installation of .
The concrete stairs and step seating are also finished. The . These will be poured within the next couple of weeks, weather permitting. The historic 1921 building is set to reopen at the start of the 2017-18 school year.
Celebrating two new theaters (March 2017)On March 16, the celebrating the opening of their two new modernized theaters. The event included a pre-show reception that honored alumni and donors and a tour of the new Bond funded performing arts facilities.
The ceremony was followed by the premier of the Social Justice Theatre Project, a student created production that shared the stories of underrepresented students through theater songs, film, and other media.
Phase II construction work on modernizing the 1921 building continues to make progress every day. On the ground floor, wall framing and mechanical, electrical, and plumbing rough-in for the classrooms on the west wing have been completed. All new concrete seismic shear walls have been completed.
Plywood diaphragm floor sheathing is nearing completion on the entire floor. Metal stud framing and mechanical, electrical, and plumbing rough-in is nearing completion at the South first floor, where the main offices and attendance are housed. On the same floor, concrete beams and columns are being formed for a science classroom and a science lab in the west wing. The east wing, where new career resource center, child care center and a mediation office will be located, scaffolding is in place to transfer building load before new fireproof steel beams become permanent structural members of the building.
On the second floor, plywood diaphragm floor sheathing is nearing completion, as well as structural steel framing. Exterior work on the 1921 building including window restoration, and masonry veneer restoration is 50% complete. In the new commons area, contractors are working on the concrete stairs, roof membrane, and skylight installation.
A New Year brings new facilities (Jan. 2016)At the end of Winter Break Roosevelt staff and students returned to a campus that had once again been transformed. This January, several new spaces are opening including the , , , new Band Room with practice spaces and the with . The new Commons, , will serve as a community gathering space and open learning area.
to return from winter break and move . “It’s like the holiday season keeps on giving.” He said enthusiastically. I’ve been dreaming about this day for months. The completion of these spaces completes Phase 1B of the Roosevelt Modernization.
Phase II, underway since this summer, will fully renovate the historic 1921 Building, that at completion will include: new classrooms, the Main Office, Counseling Center, Family Room and Albina Head Start. Seismic sheerwalls will be completed this month and structural framing will begin on the ground floor of the West wing. Significant progress has also been made on the extension to the Student Commons area.New spaces to open after Winter Break (Dec. 2016)
. Its floor has been waxed making it ready for furnishing. In the flooring and finish painting is taking place. New furniture will be installed in the coming weeks. the new ventilation and exhaust system has been put in place and kitchen appliances are being installed in the coming weeks. Near the end of the month, Roosevelt’s existing kitchen facilities will be moved from the old kitchen to the new commons/kitchen in preparation for its opening after winter break.
. Major in the West Wing. Sheer walls in the South and East Wing will be poured in the coming weeks. of the modernized building.Outside in the new commons courtyard, . Skylights are scheduled to come in early January, 2017.Finishing Touches on More New Spaces (Nov 2016)The Roosevelt High School Modernization project continues to move forward with more new buildings preparing to come online soon. Interior finishes at the Black Box theater space are complete. , fixtures and equipment (FFE) for the auditorium which is planned to be available after winter break in early 2017. . Drywall is going up and lighting and stage rigging will be brought in by the end of November. Floor finishing and carpeting are expected to be complete in early December.
workers are painting interior walls and laying down flooring. It is scheduled to be furnished during the winter break and open for class in January 2017. Dry walling and ceiling installation are in progress in the . It too expected to be open after winter break. is finishing up. Students and teachers will likely see a brand new cafeteria with spacious dining area in the east wing when they return for Spring Semester 2017.
. Abatement work and are nearly complete and concrete sheer wall construction is proceeding. The sheer walls will bring the historic building up to modern seismic safety code standards. Unforeseen conditions, such as uneven floor elevations and unreinforced masonry provide the project team’s engineers and architects with challenges to meet but the work proceeds on target. In the next couple of weeks, the construction team will continue to of the historical building.More New Spaces Coming Online Soon (Mid-Oct. 2016)knowing that even more buildings will become available just after winter break and again next fall. Work is moving ahead to complete the Auditorium, Black Box Theater, the New Commons and the Band room. These are scheduled to open after winter break in early 2017. In September, the Auditorium saw interior framing, with taping, and painting in progress. Interior finishes were also ahead moving ahead in the New Commons. In the Black Box Theater rough-in work took place.
In October work on really ramped up. A majority of the historic building has been abated and it is close to 80% complete on the demolition phase. Seismic upgrade work is also underway with the construction of sheer walls throughout the structure. These will help bring the nearly 100-year-old building into compliance with modern seismic standards and significantly improve the overall safety of the building in case of an earthquake.
Throughout October the New Commons interior finishes will continue to move forward with substantial progress taking place over the next few weeks. Kitchen work is taking place this month with new stainless equipment starting to be installed towards the end of the month. The Auditorium and Black Box are also moving forward with interior finishes with some rough-in work continuing. Stage rigging for the new auditorium should start towards the end of October. The new Band Room area is in interior finish mode and this will continue into the next month.Welcome Back to a New Roosevelt (August 2016)
Renovation work is complete on the former auditorium building, which will now serve as the new Media Center / Library with many new classrooms below. In just a few months, additional new facilities will open. These include the new Commons / Cafeteria, Band Room, state of the art Theater, and the Black Box theater classroom.
Performing Arts and Café / Commons Will Open After Winter Break
With the safety of students and staff being the highest priority, some revisions have been made to the building turnover plan that will impact the new Commons / Cafeteria, Band Room, Theater and Black Box theater classroom. These programs and activities will instead remain in the existing Cafeteria wing on North Central & North Ida for the Fall Semester.
Due to the necessary positioning of a high-boom crane necessary for renovating the historic 1921 Building, the decision was made to postpone opening the new Cafeteria / Commons and Band Room in the Fall. This was done to ensure the safety of students and staff due to the swing radius of the crane, as it brings in materials for the renovation. The location of the historic clock tower makes alternate positioning of the crane impossible.
For more details and to learn how this next phase of construction impacts students and staff view the new RHS Fall 2016 Construction Update Flyer. Español | Soomaaliga
-
Documents, Images and Details
Read the Roosevelt Project Fall 2017 Update
To view the previous project posts visit the RHS Modernization Document Archive page.
Got questions? Check out the Roosevelt Modernization FAQ
The Latest Roosevelt Construction Images
-
Video and Photo Galleries
View Roosevelt VideosView photo galleries that document the project
-
Project Schedule
Phase III Construction was completed in January 2018.
-
Get Connected
To receive updates and event notices, join the Roosevelt Project Director's Newsletter mailing list: RHSMod@pps.netIf you have construction related questions or concerns please call 1-866-686-1886
Office of School Modernization: 503-916-2222
欧美巨乳色情片 Social Media links
For general information about school building improvement bond projects email the Office of School Modernization.
-
Project Team
is the Architecture Team for the Roosevelt High School Modernization. Bassetti has a strong background in both educational projects and historic buildings. The contractor for the project is .